This page outlines the BHoM development sprint schedule for 2026. Our development cycle follows a quarterly release cadence with six two-week sprints per quarter, preceded by a planning week.

2026 Sprint Calendar


Release Schedule Overview

Release Planning Week Sprint Period Beta Release
v9.1 Dec 29, 2025 – Jan 9 Jan 12 – Apr 3 April 2026
v9.2 Apr 6 – Apr 10 Apr 13 – Jul 3 July 2026
v9.3 Jul 6 – Jul 10 Jul 13 – Oct 2 October 2026
v10.0 Oct 5 – Oct 9 Oct 12 – Jan 1, 2027 January 2027

Q1 2026 — Release v9.1

Planning Week: December 29, 2025 – January 9, 2026

Sprint Start End
Sprint 1 Jan 12 Jan 23
Sprint 2 Jan 26 Feb 6
Sprint 3 Feb 9 Feb 20
Sprint 4 Feb 23 Mar 6
Sprint 5 Mar 9 Mar 20
Sprint 6 Mar 23 Apr 3

Q2 2026 — Release v9.2

Planning Week: April 6 – April 10, 2026

Sprint Start End
Sprint 1 Apr 13 Apr 24
Sprint 2 Apr 27 May 8
Sprint 3 May 11 May 22
Sprint 4 May 25 Jun 5
Sprint 5 Jun 8 Jun 19
Sprint 6 Jun 22 Jul 3

Q3 2026 — Release v9.3

Planning Week: July 6 – July 10, 2026

Sprint Start End
Sprint 1 Jul 13 Jul 24
Sprint 2 Jul 27 Aug 7
Sprint 3 Aug 10 Aug 21
Sprint 4 Aug 24 Sep 4
Sprint 5 Sep 7 Sep 18
Sprint 6 Sep 21 Oct 2

Q4 2026 — Release v10.0

Planning Week: October 5 – October 9, 2026

Sprint Start End
Sprint 1 Oct 12 Oct 23
Sprint 2 Oct 26 Nov 6
Sprint 3 Nov 9 Nov 20
Sprint 4 Nov 23 Dec 4
Sprint 5 Dec 7 Dec 18
Sprint 6 Dec 21 Jan 1, 2027

Sprint Cadence

Each development cycle follows a consistent structure:

  • Planning Week — Backlog refinement, sprint planning, and alignment across teams
  • Sprints 1–6 — Two-week development sprints with defined deliverables
  • Beta Release — End of cycle release for testing and validation

All sprints run Monday through Friday. Sprint boundaries align to facilitate coordination across our global contributor network.


Questions?

For questions about the development schedule or contributing to an upcoming sprint, reach out via the BHoM Slack or open a discussion on GitHub.